LINKS
home page
bridges
industrial
information
rentals
windmills
gallery
 
 
 

|
|
windmill projects
  Experience That Counts
More Images

Hoover Dam Bypass Project – Boulder City, Nevada – In the spring of 2005 we were awarded a subcontract by Obayashi Corporation (Project General Contractor) to participate in the construction of one of the largest arch bridges in the world. The Hoover Dam Bypass Bridge has been in the works ever since the tragic day of Sept 11, 2001. Since that fateful day, interstate traffic has been greatly restricted for crossing the Hoover Dam. All semi trucks and other large vehicles have been rerouted to other highways around the dam for security reasons. The rerouting has added hours of extra travel time for these drivers, so the need for the Hoover Dam Bypass Bridge was very apparent. The Hoover Dam

Bypass Bridge will be the 4th largest concrete arch bridge in the world. It will span the canyon just below the Hoover Dam. Our part of this $130 million project will be to erect the 350’ tall twin cable ways that will carry the bridge material across the canyon. In addition to the cableway erection, we will erect all the vertical precast concrete columns, horizontal steel tub girders, and we will install the stay in place metal decking. This project is scheduled to be complete by late 2007 or early 2008.

Chevron Refinery – We were successful in our bid to Harder Mechanical of Portland, OR to do the majority of the structural steel and vessel installation for the Chevron Refinery upgrade in Salt Lake City, Utah. The contract required many heavy vessels to be installed and a variety of steel structures to be erected. We were asked to assist with several other items not in our contract so that the project would be finished on time. Much of the extra work was fabricated on site due to time constraints. We completed the project on time and within budget.

Holly Oil Refinery – North Salt Lake City, Utah – In October of 2005 we were contracted to lift and set a 628,000 pound vessel for Holly Oil Refinery. We used an M2250 with a Maxer 2000 attachment and a M777 truck crane to perform the lift. First we had to re-position the vessel, so we “leap-frogged” it and then stood it up, crawled it into place and installed it. The lift went very well and the vessel is up and running.

Hopkins Ridge Wind Project: Dayton, Washington – In late August 2005 we began to erect the Hopkins Ridge Wind project near Dayton, Washington. We erected 83 Vestas V80 wind turbines on 67-meter towers and finished with erecting operations just prior to the Thanksgiving weekend. This project was built for Renewable Energy Systems of Austin, Texas.

NPPD - Ainsworth, Nebraska:– In June of 2005, we began erecting activities on the NPPD wind project near Ainsworth, Nebraska. We erected 36 Vestas V82 wind turbines on 70-meter towers. We finished erecting the project one day ahead of schedule even though there were almost 4 times the number of wind days that had been expected. This project was built for Renewable Energy Systems.

Sweetwater Phase II In September of 2004 we began erecting the Sweetwater Phase II wind project for RES of Austin, Texas. This phase of the project consisted of 61 GE 1500 turbines on 80-meter towers. The erecting portion of the project was completed by mid-January of 2005

Hurricane Arch Bridge Rehabilitation – In the early summer of 2003, we began the rehabilitation of the old hurricane arch bridge. (During the first of the year we erected a sister bridge next to this historic bridge.) We removed all of the bridge super-structure, blasting, repainting, repairing, and strengthening to meet current seismic codes. We will also be widening the bridge to accommodate increased traffic into Zion’s National Park.

Henderson Interchange near Las Vegas, Nevada - We were awarded the contract for erecting two large steel “fly-over bridges at the Henderson Interchange project located at the South end of Las Vegas and I-15. We finished this erecting these overpasses early. The interchange is operational and is a big success to servicing the tremendous growth to the Las Vegas area.


 

 


  Past Projects

Eagle Canyon
I-15 Reconstruction
Cripple Creek Bridge
Olympic Pedestrian Bridge
Colorado E-470
Wind Farm - Condon, OR
Legacy Highway

Highmore, SD Wind Farm - On July 14th, 2003 we begun erecting 27 GE 1.5MW turbines on 65 meter towers for FLPE in Highmore, South Dakota. This project was finished by September, 2003.

• During late summer of 2001 we erected a pedestrian suspension bridge for the 2002 Winter Olympics in Salt Lake City, Utah. This spans 290’ across Wasatch drive found up at the University of Utah campus. There are 20 - 2-inch cables supporting the entire structure. This bridge will be used for Olympic athletes to cross the busy street from their housing to various Olympic venues.

Rock River Wyoming - Wind Farm - In July - Sept.2000, we erected 50 one-megawatt turbines in Rock River, Wyoming These turbines were manufactured by Mitsubishi Heavy Industries (MHI)

Palm Springs, CA - Wind Farm - erected 111 windmills between Nov 2000 and Sep. 2001. All turbines were on 50 or 60meter tower and were manufactured by MHI

Foote Creek IV, Wyoming - Wind Farm: In June 2000, we erected 40 - 600kW MHI wind turbines. Industrial construction

Continental Lime - Geneva Air, Utah - in 1993 we installed a new storage tank for Geneva Air Product.

Back to topˆ


1490 West 200 South Lindon Utah 84042 Phone: 801-785-8888 Fax: 801-785-0088 E-mail: info@olsenbeal.com
 
 
© 2001 OlsenBeal. All rights reserved